Exam Code: CCM
Exam Questions: 101
Certified Contract Manager
Updated: 25 Nov, 2025
Viewing Page : 1 - 11
Practicing : 1 - 5 of 101 Questions
Question 1

You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?

Options :
Answer: A

Question 2

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)? Choose all of the correct answers (multiple possibilities)

Options :
Answer: A,B

Question 3

Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?

Options :
Answer: B

Question 4

Which of the following cases will allow the Employer to claim under the Performance Security? [2017 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).

Options :
Answer: A,E

Question 5

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?

Options :
Answer: C

Viewing Page : 1 - 11
Practicing : 1 - 5 of 101 Questions

© Copyrights FreePDFQuestions 2025. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreePDFQuestions). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreePDFQuestions.