You are the Contract Manager for the Engineer in a hotel project using FIDIC Red Book (edition 1999). The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during construction. Which one of the following is NOT considered as a Variation?
For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly. When does the Contractor's reporting requirement end?
Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?
You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer's financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?
Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme? Choose all of the correct answers (multiple possibilities)