Question 1

Which additional set of test cases is needed to achieve both 100% statement coverage and 100?cision
coverage?

Options :
Answer: C

Question 2

Which statement about test automation is TRUE7 SELECT ONE OPTION

Options :
Answer: B

Question 3

How many test cases are required to test a specification that has three conditions using a decision table testing which is not collapsed?

Options :
Answer: D

Question 4

Which TWO of the following statements about Maintainability testing are TRUE?

A) It should start as soon as the draft design documents are available for review

B) An application can be considered maintainable when static analysis and code review defects have been

fixed

C) It tests the regression impact of software or environmental changes to an operational system

D) It can be performed during Operational Acceptance Testing by multiple departments

E) It can be performed during User Acceptance Testing to ensure business processes can be maintained

Options :
Answer: B

Question 5

Given the following code: If x > y and z = 3 statement! elseif z = 4 statement endif; What is the minimum number of tests needed to achieve 100% decision coverage?

Options :
Answer: B

Viewing Page : 1 - 24
Practicing : 1 - 5 of 238 Questions

© Copyrights FreePDFQuestions 2026. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreePDFQuestions). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreePDFQuestions.