Question 1

DEF, Inc. is in the ramp-up phase of a unique medical device. The device has a two-year life expectancy. The sales forecast for the ramp-up period is as follows MonthJulAugSepOctNovDecJanFeb

Unit Sales1001502006001,4002,2004,00010,000

Demand after February is expected to remain at 10,000 units per month for several months, then decrease

gradually. The units are small, and thus maintaining an inventory of up to 10,000 units is possible.

There are only three suppliers capable of providing the specialized component critical to this product. The

production capacities of these suppliers are as follows:

•Supplier X has a capacity of 500 units per month at a cost of S20 per unit, representing 80% of its total

business

•Supplier Y has a capacity of 2,000 units per month at a cost of S2O.5O per unit, representing 50% of its total

business

•Supplier Z has a capacity of 20,000 units per month at a cost of $20.70 per unit, representing 10% of its total

business

Two of these companies—Supplier X and Supplier Y—are minority businesses.

Given this situation, DEF should contract with

Options :
Answer: B

Question 2

A supply manager for JKL, Inc. is negotiating a contract with a supplier of a component. The component will be used in a new product JKL Is manufacturing and plans to bring to market early next year. Which of the following will be the MOST important provision for the supply manager to negotiate for? 

Options :
Answer: B

Question 3

XYZ, Inc. notices that one of its suppliers has been failing to achieve on-time delivery, even though XYZ sends it a 6-month projected order forecast every month. The supplier claims that it takes nine months to receive important raw materials, and that this causes the poor delivery performance. Nevertheless, XYZ must continue purchasing from this supplier, as it is a sole supplier. Given this situation, which of following is the BEST course of action for XYZ to take

Options :
Answer: D

Question 4

A firm needs to provide raw materials to accommodate a recent increase in manufacturing production. The supply manager uses the material forecast from the material requirements planning (MRP) software and the storage capacity from the warehouse management system (WMS) to forecast the firm's requirements. Which of the following will impact this forecast MOST significantly? 

Options :
Answer: C

Question 5

A manufacturer of gas-powered motors realigns its supply chain to fit a new business segment. In the past, the firm focused on customized designs. Now, it wishes to compete in the electric motor market, which is highly competitive and price-sensitive. Given this situation, which of the following will ensure that the firm has the proper planning in place? 

Options :
Answer: A

Viewing Page : 1 - 17
Practicing : 1 - 5 of 170 Questions

© Copyrights FreePDFQuestions 2025. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreePDFQuestions). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreePDFQuestions.