DEF, Inc. is in the ramp-up phase of a unique medical device. The device has a two-year life expectancy. The
sales forecast for the ramp-up period is as follows MonthJulAugSepOctNovDecJanFeb
Demand after February is expected to remain at 10,000 units per month for several months, then decrease
gradually. The units are small, and thus maintaining an inventory of up to 10,000 units is possible.
There are only three suppliers capable of providing the specialized component critical to this product. The
production capacities of these suppliers are as follows:
•Supplier X has a capacity of 500 units per month at a cost of S20 per unit, representing 80% of its total
business
•Supplier Y has a capacity of 2,000 units per month at a cost of S2O.5O per unit, representing 50% of its total
business
•Supplier Z has a capacity of 20,000 units per month at a cost of $20.70 per unit, representing 10% of its total
business
Two of these companies—Supplier X and Supplier Y—are minority businesses.
Given this situation, DEF should contract with
A supply manager for JKL, Inc. is negotiating a contract with a supplier of a component. The component will
be used in a new product JKL Is manufacturing and plans to bring to market early next year. Which of the
following will be the MOST important provision for the supply manager to negotiate for?
XYZ, Inc. notices that one of its suppliers has been failing to achieve on-time delivery, even though XYZ
sends it a 6-month projected order forecast every month. The supplier claims that it takes nine months to
receive important raw materials, and that this causes the poor delivery performance. Nevertheless, XYZ must
continue purchasing from this supplier, as it is a sole supplier. Given this situation, which of following is the
BEST course of action for XYZ to take
A firm needs to provide raw materials to accommodate a recent increase in manufacturing production. The
supply manager uses the material forecast from the material requirements planning (MRP) software and the
storage capacity from the warehouse management system (WMS) to forecast the firm's requirements. Which
of the following will impact this forecast MOST significantly?
A manufacturer of gas-powered motors realigns its supply chain to fit a new business segment. In the past, the
firm focused on customized designs. Now, it wishes to compete in the electric motor market, which is highly
competitive and price-sensitive. Given this situation, which of the following will ensure that the firm has the
proper planning in place?