Question 1

What is a strategy to reduce the number of vehicles required for building occupants?

Options :
Answer: B

Question 2

At peak occupancy a building was found to have 20 full-time employees (8 hours per day), 10 part-time employees (4 hours per day), and 50 transient occupants. Calculate the amount of peak building users.

Options :
Answer: A

Question 3

Which of the following is NOT required of an Innovation and Design strategy? 

Options :
Answer: B

Question 4

Which of the following is a benefit of stormwater harvesting?

Options :
Answer: B

Question 5

A general contractor attempts a credit in Local or Regional Materials and discovers that the specified product has only a portion of the material manufactured within the required radius. What should the general contractor do?

Options :
Answer: C

Viewing Page : 1 - 37
Practicing : 1 - 5 of 370 Questions

© Copyrights FreePDFQuestions 2025. All Rights Reserved

We use cookies to ensure that we give you the best experience on our website (FreePDFQuestions). If you continue without changing your settings, we'll assume that you are happy to receive all cookies on the FreePDFQuestions.