Whenever dissimilar metals must join, the most common practice is to
Upon arrival of coating materials, the inspector should
You are the NACE Inspector on a job where NACE No.2/SSPC - SP 10 has been specified. You are finding the Contractor is leaving mill scale on the surface and as a result you have been rejecting the blast. The Contractor is very upset and has told you that the standard permits up to 5% of the mill scale to remain and still be in compliance with the standard.
Your FIRST preferred course of action is to:
Good records can provide maintenance departments with detailed information about ALL of the following EXCEPT
When using a sling physchrometer a very large difference between the wet and dry bulb readings indicates: