A project manager of an IT company is assigned to a project whose schedule may be delayed due to a lack of resources to conclude the backlog activities. The project manager decides to hire additional developers to reduce the project's technical debt and meet the project deadline. What should the risk manager advise the project manager to do to address this situation?
The trigger for a highly categorized threat has occurred. The risk has a set response plan. Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?
In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk. What should the risk manager do?
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project. What should the project manager do next to avoid similar risks?
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning. What should the risk manager complete first?