Exam Code: Project-Management
Exam Questions: 80
ARE 5.0 Project Management (PjM) Exam
Updated: 24 Nov, 2025
Viewing Page : 1 - 8
Practicing : 1 - 5 of 80 Questions
Question 1

The architect's contract with the owner has a budget of construction cost, and the architect has established a budget of cost in the mechanical engineer's contract. The mechanical bid package is 36% over the budget. What is the engineer required to do?

Options :
Answer: B

Question 2

What is the primary purpose of a construction schedule? 

Options :
Answer: B

Question 3

The architect is on site to evaluate the completed work by the contractor. During the evaluation, the architect notices a structural connection that deviates from the contract documents. According to AIA B101, to which party should the architect report this observed deviation?

Options :
Answer: D

Question 4

According to AIA Document B201, the architect must perform which of the following services during Construction Contract Administration? Check the three that apply. 

Options :
Answer: C,E,F

Question 5

An architect is evaluating a change order. Where should the costs for the project superintendent or general foreman be included?

Options :
Answer: C